• Typical project:

    Dike surface of Thuong river, Bac Giang.

Project:

Dike surface of Thuong river, Bac Giang project.

After completing Lang Tu, Duong Huy, Viet Yen District, People’s Committee decided to construct 4.3 km of Sen Ho – Van Trung road.

This is a road with a heterogeneous soil, some weak foundation and wetting of ponds and canals on both sides of the road. On the other hand, the traffic of high tonnage> 50 tons is high (due to the sand at the end of the route).

The road will be constructed with 200 meters of reinforced surface of the dyke of the Thuong River (Dyke 3) with the material in place is entirely embankment from the old.

  • Investor:
    People’s Committee of Viet Yen district, Bac Giang province.
  • Contractor:
    Joint venture of Hai Tho Construction Company and VIETRACO.

Project details:

Investor

Investor:
People’s Committee of Viet Yen district, Bac Giang province.

Technology direction:
Mr. Nguyen Dang Hung.

Construction supervision:
Mr. Nguyen Quoc Anh.

Contractor:
Joint venture of Hai Tho Construction Company and VIETRACO.

 

Project details
  • Scale: 200m long on the dyke of Thuong River.
Completion time

Construction and completion time:

November 2016.