Investor
Investor:
People’s Committee of Viet Yen district, Bac Giang province.
Technology direction:
Mr. Nguyen Dang Hung.
Construction supervision:
Mr. Nguyen Quoc Anh.
Contractor:
Joint venture of Hai Tho Construction Company and VIETRACO.
Project details
- Size of road: Length 2,000m, width 4m.
- Design standard: Eyc> = 120 Mpa.
- Acceptance test achieved: Modyn elastic b / q: 183 MPa.
- Structural: Reinforcement of existing road bed with TS additive and cement, reinforced layer 20cm to 22cm. The surface of the reinforcing layer is covered with emulsion and 2 cm thick stone.
Completion time
Construction and completion time:
From 18/08/2016 to 30/08/2016.